The Six Links: Where Extension of Time Packages Disintegrate
Reviewing a 1,200-page claim bundle submitted by an international EPC joint venture. Massive appendices, beautifully bound charts, drone photographs of idle cranes. Total sum demanded: US$ 38m.
A claim is a chain of six unbroken links: 1) Event occurred, 2) Employer contractual responsibility, 3) Compliant notice served, 4) Physical impact on works, 5) Critical path affected in the accepted schedule, and 6) Actual substantiated cost incurred.
The bundle had 800 pages on Link 1 (event) and 300 pages on Link 6 (invoices). Links 3, 4 and 5 were covered by three speculative paragraphs.
Break one link and the chain fails. We do not write 1,200-page narratives to conceal weak links. We test all six links before serving. If Link 3 or Link 5 does not hold, we tell you on day 14, before you pay six-figure consulting fees on an illusion.
Rebuilding daily site records into a chain of evidence a tribunal can check.
Forensic schedule delay modelling, quantum substantiation, and dispute avoidance across the GCC.