Concurrent Delay: The Great Contractor Refuge

Published: 2025-12-05·5 min read·First posted on LinkedIn on 05 December 2025
01 / THE SITUATION

The employer fails to release the civil foundations for Area 3 on date X. The contractor claims 45 days EoT and full prolongation costs. The employer’s defence discovers the contractor had not even placed the purchase order for the structural steelwork due in Area 3 until six weeks later.

(- The fastest way to lose an entire claim is to let the opposing delay analyst find your unprocured equipment before you disclose it.)
02 / THE RULE THAT APPLIES

SCL Delay and Disruption Protocol (2nd edition): True concurrency occurs when two or more effective causes of delay are on the critical path at the same time, one being Employer Risk Event and the other Contractor Risk Event.

03 / THE CONSEQUENCE

The contractor might escape liquidated damages for the overlapping period under English or common law rules, but recovery of prolongation cost is completely barred because the contractor would have incurred those standing costs anyway.

04 / PRACTICE POSITION

Never build an EoT claim on an employer delay without first auditing your own procurement and subcontractor records. If you claim time for an empty foundation while your equipment is sitting unbuilt in a vendor yard, you destroy your credibility on every other package.

PROJECT MANAGEMENT SERVICES

Rebuilding daily site records into a chain of evidence a tribunal can check.

Forensic schedule delay modelling, quantum substantiation, and dispute avoidance across the GCC.