The Claim Does Not Fail on the Merits. It Fails at the Gate.

Published: 2026-02-28·4 min read·First posted on LinkedIn on 28 February 2026
01 / THE SITUATION

A contractor completes 18 complex site variations over fourteen months. The works were genuinely instructed by the engineer. The additional plant and overtime were spent. The physical delay to commissioning is beyond dispute.

(- You can argue prevention principle all the way to London or Dubai Court. The tribunal will still read the 28-day notice clause first.)
02 / THE RULE THAT APPLIES

Sub-Clause 20.1 (or 20.2 in the 2017 form): notice of claim must be served within 28 days of becoming aware of the event or circumstance, followed by a fully detailed claim within 42 days.

03 / THE CONSEQUENCE

Out of 18 events, exactly 5 carried a compliant first-limb notice. None carried the compliant 42-day follow-on submission. The employer’s legal team filed an immediate summary determination at the threshold.

04 / PRACTICE POSITION

The contractor spent US$ 4.2m proving cause, effect, and disruption optics. But the arbitrator never reached the merits. The claim failed at the gate. If your record does not prove the procedural condition precedent, your engineering file is an expensive diary.