The 28 Days Run from the Event. Not from the Delay.

Published: 2026-11-26·3 min read·First posted on LinkedIn on 26 November 2026
01 / THE SITUATION

A contractor builds a residential tower in Dubai under an amended FIDIC 1999-form contract, with disputes referred to the DIFC Courts. The trial judge finds 325 days of delay. Of those, 306 days are attributed to the employer and 19 to the contractor. The contractor still does not get its Extension of Time (EoT).

(- The delay analysis can wait. The first notice cannot.)
02 / THE RULE THAT APPLIES

Sub-Clause 20.1 of the 1999 Red, Yellow and Silver Books (Sub-Clause 20.2 in the 2017 forms): notice of claim is due not later than 28 days after the contractor became aware, or should have become aware, of the event or circumstance giving rise to the claim. In Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016 (12 May 2023), the DIFC Court of Appeal held that this notice is a condition precedent. Time runs from awareness of the event, not from the later day on which delay to completion starts. The court declined to follow the more generous reading in Obrascon Huarte Lain v Attorney General for Gibraltar [2014] EWHC 1028 (TCC).

03 / THE CONSEQUENCE

The 28-day notice was late. The original Time for Completion stayed in place and Liquidated Damages (AED 42,500 a day, capped at 10% of the contract price) ran from it. Prevention and good faith did not rewrite the bargain. The 42-day detailed claim is not a condition precedent in the same way: late or thin particulars can reduce the assessment, but do not of themselves end the entitlement. This is DIFC law applied by the DIFC Courts. It is not a decision of the onshore UAE courts, and it is not English law.

04 / PRACTICE POSITION

Keep a notice register against every late drawing, late access and instruction. Send the first notice short and early. It needs to read as a claim notice and describe the event, nothing more. A later finding that the employer caused the delay will not cure a missed 28 days.