Nine Open Points: What Still Stands Between the SHANTI Act and a Bankable Project
The SHANTI Act became law in December 2025. Draft Rules followed on 14 August 2026, and comments closed on 4 September 2026. Nine commercial papers still stand between a permitted nuclear project and one that can be financed and signed.
Commercial papers still open between the statute and a project that can be financed and signed
Tariff method, captive-power terms, grid connection, scheduling, payment security, fuel terms, foreign-investment notification, lender step-in, and land tenure. None of the nine is a safety finding.
What the statute has already settled
The SHANTI Act became law in December 2025. Draft Rules came out on 14 August 2026, and comments closed on 4 September 2026. At the date of this note the final Rules were not notified, and no date had been announced. Rules take time, and getting them right matters more than getting them fast.
A party about to commit capital is not looking at the law for permission. It is looking for a short list of papers. The Act and the draft Rules have already fixed several hard things: a single composite licence to build, own, operate and decommission; an in-principle approval that can be obtained before choosing a site or a technology; and a capped, channelled liability regime, now under challenge in the Supreme Court. That is real progress. The open points are what is left between a project that is allowed and a project that is bankable.
The nine open points
None of these is about safety. Safety is the regulator's job and should stay that way. All nine are about whether a project can be financed and signed. Any one of them, on its own, can stop a credit committee from saying yes. A reactor cannot be half-built while the answer is still open.
Grid connection, scheduling and payment security are recorded here as open, not as clauses the draft forgot. They sit under electricity practice as well as under the nuclear rules, which is why they remain open for a developer.
- Tariff. The draft says a committee set up by the Central Government will recommend how tariffs are fixed. The draft does not yet say who sits on that committee, or what method it will use. A buyer and a builder need the formula before they can talk price.
- Captive power. The draft lists captive generation as a permitted purpose. How that power reaches a factory that is not next door, and what charges apply on the way, is not spelt out.
- Grid connection. Who builds the line, who pays, and on what timeline.
- Scheduling. How round-the-clock nuclear output is treated in a grid that is increasingly solar at noon.
- Payment security. If the buyer pays late, what protects the plant: an escrow, a letter of credit, or a guarantee.
- Fuel. Enrichment and spent-fuel management stay with the Central Government, which is the right sovereign call. Price, term, and what happens if supply stops are not yet on paper.
- Foreign investment. Up to 49% through Indian-majority joint ventures has been widely signalled. The policy itself is still to be notified.
- Lender step-in. If the owner fails, can the lender take over? Neither the draft Rules nor any published model document sets out a template.
- Land tenure. The draft wants land assured until decommissioning and release from government control, and financial security held until all spent fuel leaves the storage pool. Add construction, sixty years of operation, decommissioning and fuel cooling, and together that can add up to roughly a century on the same site. That span is the sum of those stages. It is not a lease term written into the draft.
Why the gap binds a schedule
In the planning case used for this note, money starts about six years before the first unit of power is sold. The six years are a planning allowance. They are not a period fixed in the Act or the draft Rules, and they are not a reported project outturn.
What would close the gap
Four steps would move a permitted project toward one that can be signed. They are options. They are not a forecast of what the final Rules will contain.
Publish the forms with the Rules, not after them. A model power purchase agreement, a model fuel agreement and a lender direct-agreement template, released together.
State the default for captive power. If industry buying its own power is the intended first route, say so and set the charges. Builders can plan around a clear answer more easily than around an open one.
Fix the land clock. Let the lease term follow the plant's real life plus decommissioning, rather than a round number.
Publish a timeline for the Rules. Even a target quarter for the final Rules lets developers stop paying people to wait.
The law opened the activity. The paperwork decides who can carry a project through to financing and signature.
This is the first of a twelve-part series on what India's nuclear fleet actually takes. The next note treats 100 GW by 2047 as a delivery rate, not as a stock of capacity.
Every figure traces to primary sources. No claims vocabulary.
Presidential assent to the SHANTI Bill. The essay keeps the month, December 2025.
Publisher / Authors: All India Radio · As at: 22 December 2025
Open source (opens in a new tab)Public consultation on the draft SHANTI Rules and the draft SHANTI Regulations. Draft Rules issued 14 August 2026; comments closed 4 September 2026.
Publisher / Authors: Department of Atomic Energy · As at: 14 August 2026
Open source (opens in a new tab)DAE issues Draft SHANTI Rules, 2026.
Publisher / Authors: Indian Infrastructure · As at: 18 August 2026
Open source (opens in a new tab)When will India notify the final nuclear rules? Position at this date: final Rules not notified, and no notification date announced.
Publisher / Authors: energynews.org.in · As at: 12 October 2026
Open source (opens in a new tab)Draft SHANTI Rules and Regulations, 2026: key takeaways.
Publisher / Authors: Lexology · As at: 2026
Open source (opens in a new tab)Cabinet clearance reported as opening the sector to private participants, with FDI of up to 49% through Indian-majority joint ventures signalled. The policy notification itself was still outstanding.
Publisher / Authors: Energetica India · As at: December 2025
Open source (opens in a new tab)Challenge to provisions of the SHANTI Act, 2025, including the capped and channelled liability regime.
Publisher / Authors: Supreme Court Observer · As at: 1 September 2026
Open source (opens in a new tab)About six years before the first unit of power is sold. A planning allowance. Not a period fixed in the Act or the draft Rules, and not a reported project outturn.
Publisher / Authors: Planning case used for this note. No primary published source. · As at: 2026